Changes are underway as part of the Mildred Hailey Apartments redevelopment project. To help keep residents informed, below is information on upcoming construction activities and what to expect every few weeks.

Thank you for your continued patience and cooperation.

Construction Update #2 – 11/19/2026

Tree Pruning: Within the next few weeks between 8 AM and 4 PM, tree pruning will take place for one day along the southwest corridor between 50-52 Lamartine Street and the MBTA Jackson Square Station pictured below.

The equipment will be placed on the 50-52 Lamartine property, and the work will occupy no more than 50% of the corridor’s width, allowing continued access for pedestrians and cyclists. A dedicated flagger will be on site to help maintain safe passage and ensure the work zone remains clear.