Work is continuing to move forward at 960-964 Parker Street! Interior asbestos abatement is now 100% complete, while exterior asbestos abatement is approximately 67% complete.
The attached photos offer a look at the building’s current condition and the progress made through the abatement process.


With interior abatement complete and exterior work well underway, the project is moving closer to the next major milestone: demolition of the existing building. Before demolition begins, the team will need complete the necessary utility cut and caps to safely prepare the site.
We’re excited to continue making progress and look forward to sharing more updates as the site begins to take shape!