Construction Update #10 – 2/15/2023

The construction team has made significant process in the construction of 2 and 6 Lamartine! Below are current updates:

  • Continued site excavation and backfill of soils.
  • 2 Lamartine building foundation work continuing then steel installation will begin.
  • Steel installation for 6 Lamartine is near completion.
  • Upgrading of site utilities which includes water and sewer lines, and electrical.
  • Continued exploration of where upgraded utilities will be installed on Heath Street. Roadwork will begin once this exploration work is finalized.

Construction Update #9 – 1/10/2024

The construction team has made significant process in the construction of 2 and 6 Lamartine! Below are current updates:

Building % Completion Estimate | 2 Lamartine St. ~21% , 6 Lamartine St. ~20%

  • Removal of soil at construction site
  • Waterproofing of underground garage so water cannot penetrate through garage walls
  • Building infrastructure/foundation work is ongoing
  • Steel installation to potentially begin in January or February
  • Upgrading of site utilities which includes water and sewer lines, and electrical
  • Continued exploration of existing utility work on Heath Street. Roadwork will begin once this exploration work is finalized.