Construction Update #11 – 4/8/2023

The construction team has made significant process in the construction of 2 and 6 Lamartine! Swing by the construction site to see for yourself! Below are current updates:

2 Lamartine St: 27% Complete || 6 Lamartine St.: 27% Complete

  • Utility and infrastructure work onsite near 50 Lamartine St. is underway.
  • 2 Lamartine building foundation work continuing then steel installation will begin.
  • Steel installation for 6 Lamartine is complete and wood framing is ongoing.
  • Upgrading of site utilities which includes water and sewer lines, and electrical.
  • Continued exploration of where upgraded utilities will be installed on Heath Street. Roadwork will begin once this exploration work is finalized.

Interested in getting involved in construction or the trades? Check out our Job Application page for more information!