Construction Update #17 – 9/26/25

  Construction updates:

  • 2 Lamartine + Anna Mae Cole Community Center:
    • Final mechanical, electrical, and plumbing work is ongoing in the amenity spaces and large hall
    • Exterior panel installation is nearly completed
    • Unit punchlist is nearly completed
  • 6 Lamartine:
    • Unit punchlist are completed
    • Interior finishes have been completed in amenity spaces
    • Solar panel installation on the roof is completed
  • Site Work:
    • Courtyard concrete and finish work in progress
    • Pavers, metal edging, plantings, and light pole bases are being installed

3/3/25 and 3/10/25 Resident Meeting

The PowerPoint presentations below were shared during two recent meetings held by the Boston Housing Authority (BHA) to keep residents informed about the re-occupancy process for 2 and 6 Lamartine Street.

3/3/2025 Meeting: This session was held for former residents of 24 Heath Street and 960-964 Parker Street

3/10/2025 Meeting: This session was held for current residents of 265+267 Centre Street and 50+52 Lamartine Street

The BHA has contracted Judy Cohn Relocation as the relocation consultant to assist with the re-occupancy of 2 and 6 Lamartine Street. Judy Cohn Relocation will provide support to residents throughout the process, ensuring a smooth transition and addressing any concerns or questions that arise.

Construction Update #16 – 2/4/25

The construction team continues to make great progress on the construction of 2 and 6 Lamartine! Below are current updates:

  • 2 Lamartine + Anna Mae Cole Community Center: 54% Complete
    • Roof installation is nearly complete
    • HVAC and plumbing installation in progress
    • Rough electrical work is ongoing
    • Interior insulation and fireproofing ongoing
    • Drywall and taping installation has started

  • 6 Lamartine: 70% Complete
    • Unit flooring, cabinets, and finishes are ongoing
    • Final coats of paint are in progress
    • Life Safety programming and installation in progress

Construction Update #15 – 1/13/25

The construction team continues to make great progress on the construction of 2 and 6 Lamartine! Below are current updates:

  • 2 Lamartine + Anna Mae Cole Community Center: 54% Complete
    • Rough mechanical, sprinkler, electrical and plumbing installation ongoing
    • Unit framing ongoing

  • 6 Lamartine: 70% Complete
    • New permanent power equipment being delivered, with power expected mid-January
    • Window installation completed
    • Flooring & cabinetry installation in progress
    • Final electrical, mechanical, and plumbing has started
    • Life Safety installation ongoing

  • Site Work:
    • Binder coat for new road installed
    • Eversource and National Grid finishing main utility installation

Construction Update #14 – 10/28/24

The construction team continues to make great progress on the construction of 2 and 6 Lamartine! Below are current updates:

2 Lamartine St. + Anna Mae Cole Community Center Updates: 44% Complete

  • Exterior wood framing almost complete
  • Window installation is in progress
  • New electrical and plumbing utilities are in progress

6 Lamartine St. Updates: 59% Complete

  • Roof is nearing completion
  • Exterior siding is in progress
  • Window installation is complete
  • Interior framing and drywall installation is in progress
  • HVAC (heating, ventilation, and air conditioning) installation is in progress
  • New electrical and plumbing utilities are in progress

Construction Update #13 – 7/25/24

The construction team continues to make progress on the construction of 2 and 6 Lamartine! Below are current updates:

  • 2 Lamartine:
    • Steel installation is underway and wood framing will follow
  • 6 Lamartine:
    • Exterior wood framing complete
    • Window installation in progress
    • Roof installation in progress
  • Anna Mae Cole Community Center:
    • Foundation walls underway
  • Utility Work:
    • Upgrading of all site utilities which includes water and sewer lines, and electrical.
    • Continued exploration of where upgraded utilities will be installed on Heath Street. Roadwork will begin once this exploration work is finalized.
    • Utility and infrastructure work onsite near 50 Lamartine St. is ongoing.

Interested in getting involved in construction or the trades? Check out our Job Application page for more information!

Construction Update #12 – 5/22/24

The construction team continues to make progress on the construction of 2 and 6 Lamartine! Below are current updates:

  • Utility and infrastructure work onsite near 50 Lamartine St. is ongoing.
  • 2 Lamartine building foundation work close to completion then steel installation will begin, followed by wood framing
  • Wood framing for 6 Lamartine is ongoing
  • Upgrading of site utilities which includes water and sewer lines, and electrical.
  • Continued exploration of where upgraded utilities will be installed on Heath Street. Roadwork will begin once this exploration work is finalized.

Interested in getting involved in construction or the trades? Check out our Job Application page for more information!

Construction Update #11 – 4/8/2023

The construction team has made significant process in the construction of 2 and 6 Lamartine! Swing by the construction site to see for yourself! Below are current updates:

2 Lamartine St: 27% Complete || 6 Lamartine St.: 27% Complete

  • Utility and infrastructure work onsite near 50 Lamartine St. is underway.
  • 2 Lamartine building foundation work continuing then steel installation will begin.
  • Steel installation for 6 Lamartine is complete and wood framing is ongoing.
  • Upgrading of site utilities which includes water and sewer lines, and electrical.
  • Continued exploration of where upgraded utilities will be installed on Heath Street. Roadwork will begin once this exploration work is finalized.

Interested in getting involved in construction or the trades? Check out our Job Application page for more information!

Construction Update #10 – 2/15/2023

The construction team has made significant process in the construction of 2 and 6 Lamartine! Below are current updates:

  • Continued site excavation and backfill of soils.
  • 2 Lamartine building foundation work continuing then steel installation will begin.
  • Steel installation for 6 Lamartine is near completion.
  • Upgrading of site utilities which includes water and sewer lines, and electrical.
  • Continued exploration of where upgraded utilities will be installed on Heath Street. Roadwork will begin once this exploration work is finalized.