The construction team continues to make great progress on the construction of 2 and 6 Lamartine! Below are current updates:
- 2 Lamartine + Anna Mae Cole Community Center: 54% Complete
- Roof installation is nearly complete
- HVAC and plumbing installation in progress
- Rough electrical work is ongoing
- Interior insulation and fireproofing ongoing
- Drywall and taping installation has started
- 6 Lamartine: 70% Complete
- Unit flooring, cabinets, and finishes are ongoing
- Final coats of paint are in progress
- Life Safety programming and installation in progress