The construction team continues to make great progress on the construction of 2 and 6 Lamartine! Below are current updates:
- 2 Lamartine + Anna Mae Cole Community Center: 54% Complete
- Rough mechanical, sprinkler, electrical and plumbing installation ongoing
- Unit framing ongoing
- 6 Lamartine: 70% Complete
- New permanent power equipment being delivered, with power expected mid-January
- Window installation completed
- Flooring & cabinetry installation in progress
- Final electrical, mechanical, and plumbing has started
- Life Safety installation ongoing
- Site Work:
- Binder coat for new road installed
- Eversource and National Grid finishing main utility installation