Construction Update #7 – 10/5/2023

The construction team has made significant process in the construction of 2 and 6 Lamartine! Below are current updates:

  • Continued site excavation
  • Footings and foundation walls for 6 Lamartine St. have begun being poured
  • Continued temporary water bypass work
  • Completion of the removal of the underground steam tunnels
  • Exploration of existing utility work on Heath Street. Roadwork will commence once this exploration work is finalized.
  • Ongoing mockup wall construction which includes windows and storefront mock up wall.
    • Mock-ups are typically full-size representations of proposed construction, built in order to evaluate proposed design and construction details or to test for performance. Utilizing mock-ups can help prevent rework and keep a project both on time and on budget.
Site excavation, footing and building foundation installation.
6 Lamartine St foundation installation.
*Building mock-up wall construction which includes windows and storefront mockup wall.